| Data center | Capacity and timeline shared | Basis / uncertainty |
|---|---|---|
| Vineland, New Jersey | 120 MW estimated live → 300 MW by Q4 2026 | Live capacity is their estimate; full delivery remains projected. |
| Béthune, France | 60 MW live → 120 MW Dec. 2026 → 180 MW July 2027 → 240 MW Dec. 2027 | Later phases use their assumed delivery cadence. |
| Madrid, Spain | 6 MW live → 18 MW Q4 2026 | First phase operating; remaining phases projected. |
| Harlow, UK | 4.4 MW live → 22 MW Q4 2026–Q1 2027 | Detail page says Q4; timeline grid says Q1. |
| Tallinn, Estonia | 22 MW Q4 2026 | Assumes GPU deployment following Q3 site handover. |
| Romford, UK | 14 MW Q4 2026 | Assumes deployment following September handover. |
| Newport, UK | 29 MW Q4 2026 | Target appears in their timeline grid. |
| Masmiyya, Israel | 22 MW Q4 2026 | Assumes deployment after Q3 handover. |
| Beit Shemesh, Israel | 18 MW Q3 2026 → 38 MW Q4 2026 → 58 MW Q1 2027 | Projected tranche schedule; Q3 delivery isn’t marked completed. |
| Birmingham, Alabama | Handover Q4 2026 → 100 MW Q1 2027 → 300 MW Q3 2028 | Separates site handover from compute deployment. |
| Spartanburg, South Carolina | 50 MW H1 2027 | Based on AIB’s stated revenue-start window. |
| Independence, Missouri | 200 MW Q2 2027 → 1.2 GW Q4 2029 | Under construction; later expansion projected. |
| Lappeenranta, Finland | 70 MW Q2 2027 → 310 MW in 2028+ | Initial ramp tied to substation completion; grid places full capacity in Q4 2028. |
| Mäntsälä II, Finland | 70 MW Q4 2027 | Substation handover followed by deployment. |
| Site / initiative | What SMASIMHO shared | Timing / qualification |
|---|---|---|
| Oklahoma City | 145 MW+ estimate; tracker retains 100 MW+ | No opening date provided. Oct. 8 post |
| Frankfort, Indiana | 525 MW+, DataOne construction and Bloom power | No opening date; explicitly described as unofficial. Weekly review, qualification |
| Rotterdam, Netherlands | Claims Nebius will occupy 200 MW at VOLT’s planned gigafactory | No Nebius deployment date provided. Oct. 12 post |
| Hyderabad, India | Identifies a likely VOLT facility with 150 MW developer capacity | Construction starts 2027; Nebius’s allocation and opening date unknown. Oct. 12 post |
| Dubai, UAE | Potential Nebius tenancy at VOLT’s 29–129 MW project | Construction starts 2027; tenancy is their speculation. Oct. 12 post |
| Chennai, India | Hiring signals suggest another deployment | Capacity and opening date unknown. Tracker |
| Palantir / Armada modular deployments | Estimates 50–100 MW+ during 2027 | Their forecast for a distributed rollout. Oct. 9 post |